Start with what is known today.
Ask whether the condition has already occurred or is still uncertain. If a supplier has missed an agreed date, record the missed delivery as an issue. If the supplier may miss the date, describe the uncertainty as a risk.
A current issue can also create a separate future risk. An unavailable test environment is an issue today; a possible delay to acceptance testing is a future consequence you may need to manage as a risk.
Issue: “The test environment is unavailable, preventing planned testing.”
Risk: “If access is not restored by Friday, acceptance testing may finish late.”
Classify the situation, then choose the response.
| Situation | Classification | Practical response |
|---|---|---|
| A key specialist may be unavailable during cutover. | Risk | Confirm availability and prepare cover before the cutover window. |
| The specialist is unavailable and cutover preparation is blocked. | Issue | Assign cover and assess the immediate effect on the plan. |
| A supplier has missed the interface delivery date. | Issue | Agree a recovery plan and record the revised forecast. |
| The missed interface delivery may shorten end-to-end testing. | Related risk | Assess the remaining test window and agree a contingency. |
| “Please confirm supplier delivery by Tuesday.” | Action | Name an owner, set the due date and track the response. |
What belongs in each log?
For a risk register
Record a reference, the cause or trigger, the uncertain event and the potential effect on objectives. Add an owner, likelihood and impact assessment, response, review date and current status. Use your organization's agreed scoring method.
For an issue log
Record a reference, the condition that exists, when it was identified and its current effect. Add an owner, severity or priority, resolution plan, target date, status and closure evidence.
Assign follow-up work to action records where useful. A log entry explains the condition; the action explains who will do what and by when.
What to do when a risk happens.
- Confirm the event. Check what happened and when. The actual effect may differ from the original forecast.
- Record the issue. Describe the current problem and its observed impact, with an accountable owner and a response.
- Update the risk. Record that it occurred and reference the related issue. Reassess any uncertainty that still remains.
- Reconcile the report. Explain the change without counting the same exposure twice or implying that creating an issue resolved the problem.
Keep a traceable reference between related records using the fields or description available in your project system.
Review the wording against the evidence.
“Testing is late” does not explain the cause, impact or response. “Testing is one day behind the approved plan after late supplier files; the test lead is confirming recovery options” gives the team a condition it can discuss and manage.